# | Work Package 1 | Due date | Delivery date | Resp. |
MS1 | Review report of existing access management practices and used access modalities and tools monitoring tools across RIs | M18 | M22 (living document) | CNR |
MS2 | Analysis of access policies and legal framework regulating the access provision | M24 | M24 | CEAM |
MS3 | Report on access cost case studies at selected facilities | M30 | M30 | CNRS |
MS4 | Meeting held with atmospheric RI representatives to develop the common access framework based on WP1 inputs | M40 | M33 | ACTRIS ERIC |
# | Work Package 2 | | | |
MS5 | Inventory of user needs related to the access provision based on survey results | M6 | M7 (see D2.1) | FMI |
MS6 | Recommendations for targeted communication modalities | M12 | M21 (see D2.2) | UW |
MS7 | Recommendations for user feedback processing | M12 | M12 (see D2.2) | CNRS |
MS8 | Evaluation of and recommendations for optimizing the strategies implemented for the pilot access calls | M30 | M30 | ICOS ERIC |
# | Work Package 3 | | | |
MS9 | Documented connection established with the key national funding agencies, ministries and RPOs in Europe | M10 | M18 | UHEL |
MS10 | Draft on potential advanced access modalities based on interactions with the national stakeholders | M30 | M31 | TROPOS |
MS11 | Established working connections to selected countries/regions for international access modality | M26 | M31 | CNRS |
# | Work Package 4 | | | |
MS12 | Analysis of on existing training schemes in the atmospheric domain related to physical access finished | M12 | M14 (see D4.1) | TROPOS |
MS13 | Analysis of existing remote access training possibilities at the Central Laboratories of ICOS and ACTRIS | M12 | M14 (see D4.2) | UGR |
MS14 | Multidisciplinary MOOC developed | M30 | M47 | IMT |
MS15 | Serious game, tutorial videos and second version of MOOC developed | M39 | | IMT |
MS16 | Analysis of long-term strategy of training and TNA related to the three access modalities | M44 | | EMPA |
# | Work Package 5 | | | |
MS17 | User consultation on requirements for the VA01 services | M2 | M8 | ICOS ERIC |
MS18 | Mock-ups of services presented to the Steering Committee | M9 | M15 | ICOS ERIC |
MS19 | Prototype services presented to user panels | M18 | M19 | ICOS ERIC |
MS20 | Feedback meeting 1 with user panel | M30 | M32 | ICOS ERIC |
MS21 | Feedback meeting 2 with user panel, discussion of updates | M36 | M40 | ICOS ERIC |
MS22 | Feedback meeting 3 with user panel, discussion of updates | M42 | M49 | ICOS ERIC |
# | Work Package 6 | | | |
MS23 | Stakeholder Workshop | M6 | M7 | UCC |
MS24 | TNA pilots completed and questionnaires issued | M47 | M48 | FZJ |
# | Work Package 7 | | | |
MS25 | 1st call launch for TNA based on existing bestpractice and expertise across the RI | M6 | M7 | UNIMAN |
MS26 | Completion of outline timetable and programme for novel access rollout | M9 | M17 | CYI |
MS27 | Completion of 1st programme revision with WP4-6 recommendation | M12 | M17 | CYI |
MS28 | 2nd call launch for TNA | M12 | M14 | UNIMAN |
MS29 | Completion of 2nd programme revision with WP4-6 recommendation | M24 | M24 | CYI |
MS30 | 3rd call launch for TNA and VA | M24 | M19 | UNIMAN |
MS31 | Completion of evaluation of first two calls | M24 | M33 | JRC |
MS32 | Completion of 3rd programme revision with WP4-6 recommendation | M36 | M38 | CYI |
MS33 | 4th call launch | M36 | M23 | UNIMAN |
MS34 | Completion of evaluation of third call | M36 | M40 | JRC |
MS35 | Completion of evaluation of final call | M46 | M48 | JRC |
# | Work Package 8 | | | |
MS36 | Workplan for strategic and sustainable access is prepared and communicated to all WPs | M6 | M8 | CNRS |
MS37 | Preliminary work on access strategy and sustainable access provision presented to the stakeholders and RIs | M24 | M34 | FMI |
MS38 | ATMO-ACCESS conference organised with the facility managers and the PIs of the selected TNA projects, national and international stakeholders and presenting strategic access plans and option for a sustainable access to atmospheric facilities | M48 | M48 | ACTRIS ERIC |
MS39 | Draft recommendations for sustainable access presented to and discussed with the atmospheric RIs | M48 | | ACTRIS ERIC |
# | Work Package 9 | | | |
MS40 | Description of application, review and selection process for TNA to ATMO-ACCESS facilities | M5 | M6 | CNR |
MS41 | List of services available via TNA | M6 | M7 (available under each facility’s description) | CNR |
MS42 | Access Management Platform | M12 | M12 | CNR |
MS43 | Review of application, review and selection process for TNA to ATMO-ACCESS facilities | M20 | M20 | CNR |
MS44 | Updated list of services available via TNA | M44 | M44 | CNR |
# | Work Package 10 | | | |
MS45 | First version of virtual access to data curation tools for homeless data at the website atmoaccess.eu | M24 | M24 | NILU |
MS46 | First version of virtual access to the trajectory and footprint analysis service website atmoaccess.eu | M24 | M27 (see D5.4) | ICOS ERIC |
MS47 | First version of virtual access to the tools for analysing and plotting atmospheric long time series across RIs at the website atmo-access.eu | M26 | M26 | CNRS |
MS48 | Virtual access to the first version of the pilot MOOC through the website atmo-access.eu | M32 | M46 | EMPA |
MS49 | Second version of virtual access to data curation tools for homeless data at the website atmo-access.eu | M42 | M36 | NILU |
MS50 | Second version of virtual access to the trajectory and footprint analysis service website atmo-access.eu | M42 | M36 | ICOS ERIC |
MS51 | Second version of virtual access to the tools for analysing and plotting atmospheric long time series across RIs at the website atmo-access.eu | M42 | M40 | CNRS |
MS52 | Virtual access to the serious game, the tutorial videos and the second version of the pilot MOOC through the website atmoaccess.eu | M42 | | EMPA |
# | Work Package 11 | | | |
MS53 | ATMO-ACCESS Kickoff meeting 2021 | M2 | M2 | CNRS |
MS54 | Associated partnership application process defined, and call launched | M3 | M3 | CNRS |
MS55 | Development and launch of the project’s website | M6 | M1 | CNRS |
MS56 | Define CO2 monitoring compensation strategy | M8 | M6 | CNRS |
MS57 | 1st ATMO-ACCESS General Meeting (2022) | M12 | M15 | CNRS |
MS58 | 2nd ATMO-ACCESS General Meeting (2023) | M24 | M24 | CNRS |
MS59 | 3rd ATMO-ACCESS General Meeting (2024) | M36 | M36 | CNRS |
MS60 | Final ATMO-ACCESS General Meeting (2025) | M51 | M48 | CNRS |